Brazil's real capacity,
not its announced one.

Brazil has the cleanest hyperscale-scale grid in the world and one of the world's tightest water-efficiency thresholds written into tax law. Both could anchor a decade of buildout. Neither has yet produced a financed pipeline at the scale of the announcements.

Installed · end 2025 approx 1,000MW
Announced · 2030 approx 13,200MW
Financed to completion 40–55%
Binding constraint Environmental
licensing
A note from Entelligencia
Brazil in depth, in Enable Brazil.
This chapter runs a little lighter than the others in the report, by design: Brazil is covered in full depth in Enable Brazil. This page sketches the picture; the flagship maps it, operator-by-operator, named interviews, the people of the market. Publishing Q3 2027.
Convenings
New York · May 2027Brazil Week · São Paulo · September 2027
Analyst overview

What the Brazil picture actually shows.

The structural advantages are real. The pipeline is not.

Brazil enters 2026 with the cleanest hyperscale-scale grid of any major market, approx 85% renewable, anchored in hydroelectric capacity that no peer can match. Microsoft and Amazon have committed a combined USD 4.5 billion in cloud-and-AI capex. The Provisional Measure that became ReData put one of the world's tightest WUE thresholds into law. The country has, on paper, the foundation for the largest renewables-anchored AI infrastructure market in the southern hemisphere.

And yet, as of May 2026, the implementing decree for ReData has not been issued. Fitch and other observers have flagged the delay. Projects announced since early 2025 remain on hold pending clarity on the thresholds. The headline 13.2 GW MME grid-connection queue, repeated across global press as Brazil's 2030 number, is, on Entelligencia's modelling, only 40 to 55 per cent financed to completion. The rest is conditional on incentives, offtake, or capital that has not yet closed.

The thesis for the chapter is this: Brazil's binding constraint is not power, water, capital, or land. It is regulatory clarity, plus a transmission build-out from the renewable-rich Northeast to the demand-rich Southeast that has not been committed at the scale required. Until both move, the gap between Brazil's announced and delivered capacity will continue to widen, and the operators who actually deliver, verified below, will hold disproportionate market share.

Entelligencia desk · South America · chapter 04 of 10
At a glance · the index

Brazil’s preconditions, scored.

Each spoke is one precondition, scored 0 to 10 for like-for-like reading – indicative editorial weighting, not a published index. Select any spoke or row to read the factor.

From announcement to live MW

Where Brazil's pipeline holds, and where it breaks.

ENT · BRAZIL · THE PIPELINE
The energy pipeline
From announcement to live megawatts.

Clean generation, transmission and the regulatory gate that throttles delivery. Open the pipeline to model where Brazil's queue holds, and where it breaks.

Brazil · May 2026

Pipeline blocked at Permitting. The decree gate is the binding constraint.

Delivered MW
approx 1,000
7.5%
of 13.2K announced
0 3.3K 8.8K 13.2K MEGAWATTS · 2030 ANNOUNCED 01 LAND 02 CLEAN POWER 03 GRID 04 PERMITTING 05 WATER 06 OFFTAKE
GATE 01 Holds
Land
SP, RJ and the Northeast all have available industrial land. Not the binding constraint.
GATE 02 Holds
Clean power
approx 85% renewable grid. Structural advantage no peer market currently matches.
GATE 03 Conditional
Grid interconnect
SP queue manageable. Northeast→Southeast transmission is the bottleneck.
GATE 04 Blocked
Permitting
ReData implementing decree still not issued. Pipeline on hold since Q1 2026.
GATE 05 Conditional
Water / WUE
0.05 L/kWh threshold rules out evaporative cooling. Closed-loop required.
GATE 06 Conditional
Offtake
Hyperscale capex committed. Site-by-site offtake not yet named.
Analyst read

Brazil's pipeline is not constrained by power, land, or capital. It is constrained by the ReData implementing decree, which has not been issued. Until it is, the announced-vs-delivered gap continues to widen.

The capacity ledger

Behind the gap: every project in the pipeline, tagged by what's been delivered.

Brazil capacity ledger · live
ENT-BR-LEDGER-2026.05 · 8 of 31 shown
Verified

Independently confirmed. Construction or operation visible on-site or in regulatory filings. Cross-referenced against grid-connection queues, power-purchase filings, and published reporting.

Announced

Press release, no independent confirmation. Project publicly announced but financing-to-completion, permitting, or offtake not yet verified.

Contested

Named source disputes the public figure. A senior operator, regulator, or financier has indicated the announced figure is materially overstated, conditional, or unfinanced.

Status
All Verified Announced Contested
Region
All São Paulo Northeast Multi-site
8 projects · approx 2,420 MW shown
Project Location Announced Verified live or in build Status Binding constraint
Ascenty SP4 expansion
Digital Realty / Brookfield
Hortolândia, SP
Campinas corridor
68MW
68MW
Verified
Grid interconnect timing
What we verified

Construction visible on-site in publicly available imagery. Power allocation cross-referenced against ONS interconnection record. PPA in place with CPFL for hydro-anchored supply. Tenant migration underway from SP3.

What would change the tag

A material delay on the second 34 MW phase, currently scheduled for Q4 2026, would move that phase to Announced. The verified figure here covers only the first phase.

Sources

ONS interconnection queue · CPFL PPA filings · Reuters · Valor Econômico.

ODATA SP02
Aligned Data Centers
Santana de Parnaíba, SP
São Paulo metro
36MW
36MW
Verified
Water permitting (resolved)
What we verified

Live tenant operation. Closed-loop cooling design indicated in ODATA / Aligned public materials. Targeted to operate below the ReData WUE threshold of 0.05 L/kWh.

What would change the tag

Operational. A change in tag would require evidence of off-spec performance or unannounced shutdown.

Sources

ODATA / Aligned press materials · São Paulo state water authority filings · Data Center Dynamics · Reuters.

Elea AI campus, Tamboré
Elea Data Centers
Tamboré, SP
Alphaville corridor
24MW
24MW
Verified
Resolved · liquid-cooled
What we verified

Brazil's first purpose-built AI data centre on liquid cooling. CDU-based deployment delivered by Vertiv. PUE band of 1.15–1.20 referenced in Elea and Vertiv joint materials.

What would change the tag

The flagship Elea facility is live and operating. Future phases are tracked separately and currently sit under Announced.

Sources

Elea + Vertiv joint announcements · Frost & Sullivan 2025 · Data Center Dynamics · Valor Econômico.

Partner case study
Vertiv
The CDU rollout that anchored Brazil's first AI build
Hundreds of coolant distribution units · 100 kW per rack · Frost & Sullivan 2025 LATAM Company of the Year
1.15–1.20
Measured PUE
2024 →
Live, scaling
Read the case →
Microsoft Brazil cloud + AI commitment
Multi-site
SP / RJ, not yet named
$2.7bnCapex
Not disclosed
Announced
ReData implementing decree
Why this is Announced, not Verified

The headline capex figure has been publicly committed but no MW figure has been published by Microsoft for the Brazil deployment, and the deployment timing is partially conditional on ReData's implementing decree. As of April 2026, the decree has not been issued. Fitch and other observers have flagged that this delay is pressing on the wider Brazil pipeline.

What would move it to Verified

A site announcement with named operator partner, grid-interconnection filing, and the ReData implementing decree being issued with WUE and clean-power thresholds intact.

Sources

Microsoft press release · Fitch Ratings commentary · ReData public consultation documents · Reuters · Bloomberg.

Amazon Brazil cloud + AI commitment
Multi-site
SP-led
$1.8bnCapex
Not disclosed
Announced
ReData implementing decree
Why this is Announced, not Verified

Capex figure committed publicly. No MW disclosure, no site selection disclosure, no operator partner publicly identified for the deployment. Sits behind the same ReData policy gate as the Microsoft commitment.

What would move it to Verified

Named site, named operator partner, grid-interconnection filing or evidence of construction.

Sources

AWS Brazil announcement · Reuters · Folha de S.Paulo · Data Center Knowledge.

Scala AI City, Tamboré
Scala Data Centers
Tamboré, SP
Alphaville corridor
450MW
approx 80MW
Announced
Substation + offtake
Why this is Announced, not Verified

Land and substation work confirmed for the first phase (approx 80 MW); that phase would qualify as Verified on its own. The 450 MW campus-wide figure is contingent on additional offtake announcements not yet public. We split the project rather than tag the whole as Announced.

What would move the campus figure to Verified

A second hyperscaler offtake announcement on top of the existing first-phase commitment, with corresponding grid interconnection filings.

Sources

Scala public announcements · ONS queue filings · Bloomberg · Valor Econômico · Data Center Dynamics.

Northeast AI corridor (composite)
Multiple announced operators
Ceará / Pernambuco / RN
Cable-landing corridor
approx 3,200MW
approx 40MW
Contested
Offtake + transmission
Why this is Contested

Aggregate announced capacity across the Northeast corridor exceeds three gigawatts. Cross-referenced against MME grid-queue filings and named financing, Entelligencia assesses a significant share of these announcements as materially overstated or unfinanced. Transmission capacity from the renewable-rich Northeast to demand centres in the Southeast has not been built at the scale required.

What would change the tag

Named transmission build-out commitments by ONS / MME, plus offtake agreements for specific named operators in the corridor.

Sources

MME grid-queue analysis · Reuters · Financial Times · Valor Econômico · Entelligencia cross-reference against publicly named projects.

Aggregate "2030 hyperscale pipeline"
Industry body composite
Brazil-wide
All regions
approx 13,200MW
approx 1,000MW today
Contested
Composite
Why this is Contested

The 13.2 GW figure is the MME grid-connection request pipeline, repeated in media as "Brazil's 2030 capacity". The Entelligencia view, cross-referenced with the named advisory council, is that 40 to 55 per cent of that pipeline is currently financed to completion. The rest is conditional on incentives, offtake or capital that has not yet closed.

What would change the tag

The ReData implementing decree being issued with thresholds intact, plus a wave of named offtake announcements moving aggregate financed share above 70%.

Sources

MME grid queue · ANEEL filings · Entelligencia aggregation · Reuters · Valor Econômico · Bloomberg.

Last verified · 12 May 2026 · 8 of 31 tracked projects shown
The file

Six findings behind the gap.

Findings dossier · BRA
Compiled May 2026
Verified Announced Contested Select any finding to open the evidence
Exhibitsthree campuses behind the headline numbers
The TikTok and Casa dos Ventos campus at Pecem, Ceara
EXHIBIT A · CEARATikTok and Casa dos Ventos, PecemHeadline USD 37.7 billion, 300 to 900 MW, wind-powered, targeted 2027.
The Scala AI City campus at Eldorado do Sul
EXHIBIT B · RIO GRANDE DO SULScala AI City, Eldorado do SulA 5 GW grid authorisation, one of the largest ever issued in Brazil.
The Tambore campus at Barueri, Sao Paulo
EXHIBIT C · SAO PAULOTambore campus, BarueriAt 450 MW IT capacity, the largest campus in Latin America.
The document

The paper trail, annotated.

Three primary sources behind Brazil’s build: the tax regime, the energy signal and the grid queue, each graded claim by claim against the record. Select a tab to bring a document forward, an underlined claim to read the analysis, or filter by grade.

Source ·   · marked by Entelligencia
Filter
The people

Who actually decides Brazil's data-centre buildout.

Hover ↻
Eduardo Zago de Carvalho
Managing Director, LATAM · Equinix
Profile · 01 of 04
Eduardo Zago de Carvalho
Managing Director, Latin America · Equinix
Influence
Interconnection, ecosystem growth, LATAM expansion. 8 Brazilian DCs, a 9th in pipeline, 5 more properties acquired.
Working on
Land pipeline, tax reform as AI catalyst, hyperscale + edge + retail.
Brazil is priority region. Plenty of space and financial resources.
Reuters · Oct 2025
Hover ↻
Christopher Torto
Founder & CEO · Ascenty
Profile · 02 of 04
Christopher Torto
Founder & CEO · Ascenty
Influence
38 LATAM data centres operating, in build or development. 750+ customers. The signature LATAM build-out story.
Working on
Disciplined scaling, AI-led demand, 100% SLA culture. View: $1bn+ deals are now the norm in Brazil.
Grow with discipline, deliver at scale, move infrastructure forward in LATAM.
The Tech Capital · 2025
Hover ↻
Ricardo Alário
CEO · ODATA, an Aligned company
Profile · 03 of 04
Ricardo Alário
CEO · ODATA, an Aligned Data Centers company
Influence
DC SP04 Osasco: 48 MW, USD 450M, first Delta³ cooling in Brazil. 100% renewable across BR sites.
Working on
Post-Aligned integration. AI/HPC density. Land-and-power-first across the Americas.
Speed-to-market at a velocity otherwise unknown in our business.
Aligned announcement · 2024
Hover ↻
Alex Sasaki
VP, Latin America · Vertiv
Profile · 04 of 04
Alex Sasaki
Vice President, Latin America · Vertiv
Influence
The enabling infrastructure layer. Frost & Sullivan 2025 LATAM Company of the Year, AI & HPC.
Working on
Scalable power and cooling for AI density. Liquid-cooled deployment economics. LATAM ecosystem.
Brazil is at a turning point to become a global data center hub.
GRI Institute · Oct 2025
+96 mapped in Enable Brazil
The full people-map · Q3 2027
The wider map
The full people-map
Brazil's data-centre decision-makers
Scope
Around 100 named operators, hyperscaler leads, investors, regulators and AI-side decision-makers across the Brazilian market.
In Enable Brazil
Each profile carries on-record positioning, working priorities, and the project they actually shipped.
The people-map is the part of Enable Brazil readers will return to twelve months after publication.
Editorial brief · 2026
The supply chain

From capital to compute · who’s active in Brazil

Brazil supply chain · live
Hover any node · Click for detail
Investors
Brookfield
KKR
GIC
Patria
BTG
DigitalBridge
BNDES
Suppliers
Vertiv
NVIDIA
Schneider Electric
ABB
Cummins
Trane
Caterpillar
DPR Construction
Operators
Ascenty
ODATA
Scala
Elea
Tecto
Equinix
Hyperscalers
Microsoft
AWS
Google
Oracle
Meta
IBM
Corporates
Itaú
Bradesco
Nubank
Petrobras
Vale
Mercado Libre
Magazine Luiza
AI workloads
OpenAI
Anthropic
Mistral
Cohere
Stability AI
xAI
Flow

Capital flows left to right, from investors through suppliers and operators to the hyperscalers, corporates and AI workloads that consume the stack. Hover any node to trace its position. Click for the company brief.

06 tiers · 41 entities
Voices of the industry

[Placeholder] What the people building it say.

Three industry voices on the supply chain, each opening a pop-out that can carry a voice clip, an interview, an opinion with exhibits, or a simple quote. Placeholder cards for now; real names, photos and content to follow.

Voice clip
[Name to come]
[Role] · [Organisation]

[Placeholder] A short standfirst on what this voice adds to the supply-chain picture.

Listen
Interview
[Name to come]
[Role] · [Organisation]

[Placeholder] A short standfirst on what this voice adds to the supply-chain picture.

Read
Opinion
[Name to come]
[Role] · [Organisation]

[Placeholder] A short standfirst on what this voice adds to the supply-chain picture.

Open

Placeholder module · voices, photos and content to be added chapter by chapter.

The wider programme

More in Enable Brazil.

Brazil is one chapter. The flagship publishes Q3 2027, with four quarterly briefings and three convenings between now and then.